| Client: |
SOLETANCHE BACHY HOLDING - CPC |
| Location: |
Fray Bentos, Uruguay |
| Period: |
2002 - 2003 |
| Cost: |
US$ 36.000.000 |
| Services: |
|
Project description:
The project consists in the development of a terminal for loading
forest products, tree trunks and wood chips.
It may be considered unique since the pier front is made of a cellular
cofferdam wall and all the operating pavements made of post-stressed
reinforced concrete.
The firm elaborated the control design and method for the sand
fillings in the interior of the cells and in the beach behind them,
the basic and detailed engineering project for the whole reinforced
concrete superstructure, gravity walls on top of cofferdam, mooring
walls, lane beams, etc., and the post-stressed pavement, with its
test and control methods.
We also designed the signaling and navigation aid systems. |